Main Street Improvement Project
Construction is on hold for the winter and will resume in the spring.
Parking - where can I park during construction?
Project Highlights: a closer look at some of the changes to occur with the Main Street Improvement Project.
Traffic and Pedestrian Plan: conceptual overlay showing the new traffic lane pattern and the locations of crosswalks.
Plans available to view here: full set of site plans for the entire project.
Sign up for CodeRed updates here
WARE INTERSECTION IMPROVEMENTS @ MAIN STREET, WEST STREET, NORTH STREET, SOUTH STREET & CHURCH STREET.
TWO LANES OF TRAFFIC WILL BE OPEN DURING CONSTRUCTION.
ACCESS ALONG SIDEWALKS HAS BEEN ASSURED DURING CONSTRUCTION. These may be effected on a day by day basis.
Timeline:
- Water Service Extensions completed
- In-Road Drainage Structures and Pipes - Main Street completed
- 4/28-5/7: Furnish & Install In-Road Traffic Signal & Lighting Conduits
- 5/18-5/22: Furnish & Install In-Road Traffic Signal & Lighting Conduits
- 5/25-5/29: Furnish & Install In-Road Traffic Signal & Lighting Conduits
- 6/3-6/5: Remove & Reset Hydrant Pipes and Gate Boxes - Main Street
- 6/8-6/18: Furnished & Install In-road Traffic Signal & Lighting Conduits with Concrete Encasement
- 6/15-6/16: Remove & Reset In-Road Hydrant Pipes & Gates Boxes
- 6/29-7/17: Install New / Reuse Existing Granite Curbing
- 7/9-7/15: Furnished & Install Lightpoles - Main Street
- 7/6-7/17: Prepare Traffic Signal Equipment, Mast Arm & Pole. Location 1.
- 9/8-9/18: Excavate and gravel concrete sidewalks
- 9/14-9/25: Install concrete sidewalks
- 10/5-10/9: Install planter
- 10/5-10/16: Install concrete sidewalks
- Work will be back filled daily, and patched with hot mix asphalt on Fridays.
- Construction timeline may change as needed due to weather, supply chains, emergencies, and COVID-19.